Infrastructure projects

  • Local development plan of Kouadioblékro

Local development plan of Kouadioblékro

  • Realization: 2014

Establishing a management plan for Kouadioblékro includes the locations of the refuse site, community toilets, wastewater collection centers and different lots that will be used for the construction of buildings needed for the development program.

Realized
  • Drinking Water Supply (DWS)
  • Infrastruktur Projekt Trinkwasser

Drinking Water Supply (DWS)

  • Planning: 2014
  • Realization: 2019
  • Commissioning: subject to availability of resources
  • Estimated number of workplaces: 1 (maintenance)

Construction of a water tower and its connection with existing clinic , school and the «sous-prefecture» are considered critical / important. Then connecting to future central sites such as the technical center, the reception center, computer center, medical center, boarding center and the city call.

Realized
  • Enactment of the communal hygiene

Enactment of the communal hygiene

  • Planning: 2014
  • Realization: 2019/20
  • Commissioning: subject to availability of resources
  • Estimated number of workplaces: 4

Training in waste management at the municipal level and management of the refuse site.

Hygienic toilets by area.

Support the project (partially realized)
  • Road development

Road development

  • Planung: 2014
  • Realization: 2019/20
  • Commissioning: subject to availability of resources
  • Estimated number of workplaces: 10 (maintenance)

To facilitate the movement of cars, vans and ambulances, set up a development and maintenance master plan of the roads between the villages of the «sous-préfecture» to Bocanda. The road network connecting all fifteen (15) villages is about 200 km

Support the project (to be done)
  • Infrastruktur Projekt Wohnquartier für Dienstwohnungen - Beherbergungszentrum

Housing complex for department heads - Visitor Centre

  • Planning: 2014
  • Realization: 2019/20
  • Commissioning:subject to availability of resources
  • Estimated number of workplaces: 4 (Caretaker, Garden, Security)

Building of a housing complex comprising five (5) houses of four (4) rooms for each department head, some of which have already been appointed (doctor, school inspector, brigade commander, school principal, etc..) Building as well twenty five (25) houses of three (3) rooms (for approximately fifteen (15) teachers, polices, nurses and midwives) and also visitor center with three (3) bedsits for teachers / doctors / Instructor and temporary staff.

The construction costs for a four bedroom apartment are around CHF 35’000.00